Overview

Name
ST WILLIAMS PRIMARY SCHOOL HEATING UPGRADE
Client
Norfolk Property Services
M&E Order Value
£350,000
Contractor
Dodd Group
ME Design Build
Dodd Group
Location
Norwich

Dodd Group was appointed as theprincipal contractor on this project. The existing heating system within theexisting primary school was beyond economical repair. The scopeof works consisted of stripping out the existing heating distribution,installing new distribution pipework and radiators, chemically treating the newsystem and commissioning of the new works.

No design documents were produced,therefore Dodd Group had to understand the Employers Requirements, attend siteto carry out surveys and develop a design solution before the installationphase was undertaken. Dodd Group also carried out the builder’s work inconnection and made good where necessary.

All works had to be undertaken outof school term times. This presented a challenge due to the time constraints,however the installation works were successfully completed during the schoolsummer holidays, whilst the water treatment and commissioning was successfullycompleted during the Autumn half term. 

Discover more major projects we’ve done in the past few years

From high security to high-rise, our expert teams have a wealth of experience in every kind of properties.

Education

The Kings Church of England School

Education
Education

Harrow ESFA Schools

Education