Hugh Baird College

Liverpool

Home / Case Studies / Hugh Baird College

Overview

Name
Hugh Baird College
Client
Sefton Council
M&E Order Value
£1.1m
Contractor
Wates Construction
Consultant
Foreman Roberts
Framework
North West Construction Hub
Location
Liverpool

The project build was procured under the North West Construction Hub Framework. The project had a 36 week M&E duration.

The new build college was a £5.5m construction project and included teaching spaces, creative arts centre, a learning resource areas, a public cafe and a Job Centre Plus for community use.

The 2,601sqm new facility included all aspects of mechanical and electrical energy efficient systems such as photovoltaic panels, air source heat pumps, solar thermal for domestic hot water systems, natural ventilation and rainwater harvesting.

Discover more major projects we’ve done in the past few years

From high security to high-rise, our expert teams have a wealth of experience in every kind of properties.

Education
Education
Education

Coed Eva Primary School

Education